Floor and wall material cleared before a Spanish Revival bathroom remodel
Example project
- Home
- 1920s Spanish Revival house in Los Angeles with a single bathroom and a 1960s update to the floor and tub wall
- Original request
- Replace the tub with a walk-in shower and lay a new floor, under a building permit from LADBS
- Testing
- A Cal/OSHA-certified asbestos consultant samples the floor vinyl and its backing, the wall skim coat behind the tub, the sink wall texture and the ceiling
- Found
- Asbestos in the sheet vinyl with its backing and in the skim coat behind the tub
- Clear
- The sink wall texture and the ceiling
- Area
- About 135 sq ft, 45 of floor and 90 of wall
- Timeline
- Notice no later than 10 working days ahead, then three working days
- Cost
- $4,100
Scope of work
The price covers removal of the vinyl, its backing and the skim coat, the bathroom sealed in plastic with air filters running, wet removal into labeled bags and a haul with its paperwork. The survey, the district notification fee, the clearance air test and the new shower and floor are separate.
Project overview
In this example, a couple in a 1920s Spanish Revival house wants a walk-in shower where the old tub sits. For this permit LADBS counts a remodel like a demolition, so it releases the permit only with evidence that the Rule 1403 notice was filed or a signed statement that notification does not apply.
The vinyl and the wall skim coat test positive, so notification applies. The abatement contractor files the notice online and the couple hands the evidence in at the permit counter. The abatement crew removes the two materials before the plumber opens the wall.
The goal
The goal is a bare bathroom with no positive floor or wall material left, so the shower goes in and the permit papers are complete.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the floor, the tub wall, the sink wall and the ceiling.
- Before work The contractor files the district notice online, and the notice evidence goes in with the LADBS permit papers.
- Days one to three The bathroom is sealed, the skim coat and the vinyl come off wet, and the bags leave with a hauler.
- Last An independent consultant tests the air, then the plumber starts on the shower.
Planning right
- Ask the consultant to mark every sample spot on a plan of the bathroom.
- Keep the notice evidence with the permit papers.
- Walls that tested clear can come down with the tub on demo day.
- Book the tile setter for after the air test.